Document compiled in accordance with BTS-AI DOPRO Guidelines on Backward/Reverse Planning.
As defined in the course material, Retro Planning (Backward Planning) is constructed in reverse chronological order from a fixed deadline. This ensures that the D-Day (Capstone Submission) is immutably fixed, and all prior sprints and tasks are mathematically bound to ensure the feasibility of the project.
Our delivery date is set for May 15th, 2026.
gantt
title Local Food AI - Capstone Reverse Plan
dateFormat YYYY-MM-DD
axisFormat %m-%d
section Delivery & Sign-off
Final Capstone Submission :milestone, m1, 2026-05-15, 0d
Disaster Recovery & PoC Test:done, 2026-05-13, 2d
Documentation Finalization :done, 2026-05-11, 2d
section Feature Freeze
Web Search (SearXNG) Integration :done, 2026-05-12, 1d
Medical Constraints & PDF Export :done, 2026-05-09, 3d
AI Meal Planner (Ollama 1B) :done, 2026-05-05, 4d
section Core Architecture
Plate Builder & Macros :done, 2026-05-01, 4d
Clinical Explorer Search :done, 2026-04-28, 3d
Zabbix Telemetry & SNMP :done, 2026-04-26, 2d
section Foundation
OpenFoodFacts Ingestion (3GB) :done, 2026-04-20, 6d
Docker Multi-Container Setup :done, 2026-04-18, 2d
Taiga/Git Agile Integration :done, 2026-04-15, 3d